Zubair 1 Depot — Actuator Replacement for Large-Size Valves
EPC project to replace Rotork actuators with AUMA actuators in Zubair 1 Depot, including engineering, installation and commissioning for large-size 42” and 36” valves.
View project & photosSelected projects demonstrate PVE’s experience in valve automation, plant retrofit and engineering execution — with real photographs from site.
EPC project to replace Rotork actuators with AUMA actuators in Zubair 1 Depot, including engineering, installation and commissioning for large-size 42” and 36” valves.
View project & photosEngineering, design, procurement, installation, testing and commissioning of a complete valve automation and control system for the PS1 & PS2 facilities.
View project & photosComplete design, engineering, supply, installation, testing, commissioning and start-up of AUMA PROFOX electric actuators replacing existing pneumatic actuators and air supply systems.
View project & photosComplete EPC and automation solutions for gas, demineralised water, service water and raw water tanks and utility facilities.
View project & photosComplete EPC project for the replacement of more than 50 Chinese electric actuators with AUMA actuators.
View project & photosTurnkey, EPC, supply, service, training and commissioning references across key industrial sectors.
AUMA actuators, gearboxes, control integration, large-size valve retrofit
Design, engineering, installation, commissioning, welding and field modification
VENTIL valve testing machines, calibration, maintenance and certification
Hot tapping machine, flowmeters, cable lugs, membranes, filters and marine fenders
| Type | Project / scope summary | PO / Ref. | Year | Status | Customer / site |
|---|---|---|---|---|---|
| EPC / Turnkey references Oil, power, utility & industrial automation projects | |||||
| Turnkey | Zubair One Depots: replacement of 48” and 42” old actuators with AUMA actuators, controls and gearboxes; Qty 50. | PVE 5-2024 | 2024 | Completed | Basra Oil Company |
| Turnkey | Zubair Two Depots: replacement of 48” and 42” old actuators with AUMA actuators, controls and gearboxes; Qty 54. | PVE 02-2025 | 2025 | Completed | Basra Oil Company |
| Turnkey | Supply and installation of valves and actuators for Al-Sader Power Plant; complete site execution; Qty 26. | PVE 01-2025 | 2025 | Ongoing | State Company for Mining Industries |
| Turnkey | Tank rehabilitation: triple-offset CRANE valves, AUMA actuators, PLC and radar system; removal, cutting/welding, testing and handover. | PVE 09-2024 | 2024 | Completed | Al-Sadar Power Plant |
| Turnkey | Replacement of existing actuators with AUMA electric actuators; valve/interface assessment, mechanical removal, electrical works and commissioning. | PVE 10-2023 | 2024 | Completed | Al-Zubaydah Power Plant |
| EPC | Replacement of tank valves and actuators, sizes 2” – 14”; Qty 18. | PVE 31-2025 | 2025 | Ongoing | Al-Sader Power Plant |
| Turnkey | Pneumatic-to-electric actuator conversion — AUMA PROFOX Qty 24; power/control panels, decommissioning air system, installation and handover. | PVE 25-2023 | 2024 | Completed | Al-Sadar Power Plant |
| Supply references Valves, actuators & piping equipment | |||||
| Supply | Axial check valves: 16” CL300, 24” CL300, 18” CL150, 30” CL150 and 26” CL600; Qty 8. | PVE BGC-4-2024 | 2024 | Completed | Basrah Gas Company |
| Supply | Butterfly valves with AUMA actuators and gearboxes; Qty 32. | PVE 30-2023 | 2024 | Completed | South Refineries Company |
| Supply | Dual plate check valves, 24” Class 600; Qty 2. | PVE-BGC-8-2024 | 2024 | Completed | Basrah Gas Company |
| Supply | Swing check valves: 12” Class 2500 and 10” Class 150; Qty 8. | PVE 05-2024 | 2024 | Partially delivered | Al-Zubaydah Power Plant |
| Supply | AUMA actuators, controls and gearboxes; Qty 54. | PVE 13-2024 | 2024 | Delivered | Nasiriya Power Plants |
| Supply | Solenoid valves; Qty 32. | PVE-MOE-13-2024 | 2024 | Delivered | Al-Sader Power Plant |
| Supply | Adjustable choke valves, 4.16 Class 1500; Qty 8. | PVE 22-2023 | 2024 | Delivered | Thi-Qar Oil Company |
| Supply | Butterfly valves 20” with AUMA actuators; Qty 4. Tender No. 2024/7068. | PVE-SRC-09-2024 | 2024 | Completed | South Refineries Company |
| Supply | Valves 16” and 8” with AUMA actuators; Qty 6. | PVE 1-2024 | 2024 | Delivered | Basra Airport |
| Supply | AUMA actuators, controls and gearboxes; Qty 15. | PVE 18-2024 | 2024 | Delivered | Bazyan Power Plant |
| Supply | AUMA spare parts for Khormala Power Plant. | PVE 42-2025 | 2025 | Delivered | KAR Company for Electricity Power Production |
| Supply | Ball valves. Tender No. 3-20-7043. | PVE 26-2023 | 2023 | Completed | Thi-Qar Oil Company |
| Specialized equipment & services Valve testing, hot tapping, flow measurement & industrial supply | |||||
| Service | VENTIL equipment calibration, maintenance and certification. | PVE 04-2025 | 2025 | Completed | Basrah Gas Company |
| Supply + Training | TD-Williamson hot tapping machine supply and training. Tender No. 9025/24/28. | PVE 22-2025 | 2025 | Ongoing | Basra Oil Company |
| Supply | Cable lugs. Tender No. 8001/24/61. | PVE 10-2025 | 2025 | Completed | Basra Oil Company |
| Supply | VENTIL device spare parts. | PVE 20-2025 | 2025 | Completed | Petronas |
| Supply + T&C | VENTIL valve testing machine, calibration, training and commissioning. | PVE 35-2025 | 2025 | Ongoing | Petronas |
| Supply | Clamp-on flowmeters; Qty 2. | PVE 36-2025 | 2025 | Ongoing | Basra Oil Company |
| Supply | VENTIL Test Orbit 24 with spare parts. | PVE-BGC-11-2024 | 2024 | Completed | Basrah Gas Company |
| Supply | Nitrogen membranes. | PVE-Bonatti-07-2024 | 2024 | Completed | Bonatti |
| Supply | Air filters. Tender No. 94-17-8040. | PVE 17-2023 | 2023 | Completed | Basra Oil Company |
| Supply | Marine fenders. Tender No. 32-20-7014. | 32-20-7014 | 2023 | Completed | Basra Oil Company |
A selection from 90 listed references. Full reference portfolio available in the company profile (PDF).